News & Construction Update June 2020

We are delighted to share with you another construction update for our benchmark new community Smiths Lane. The site is currently buzzing with construction activity, with our team making great progress since commencement onsite earlier this year.

 Key construction milestones include:

Stages 1 & 2 
Sewer & drainage complete. Water and electrical works are commencing soon. Servicing of the stage is well underway. 

Stage 3 
Earthworks are complete with sewer with drainage nearing completion.

Stages 4, 7 & 8 
Earthworks are complete with civil works expected to begin with the coming weeks.

Clyde Grammar
Handover of the school site is on track for the end of 2020, with construction of the new campus anticipated to begin early 2021. 

Thompsons Road & Smiths Lane
The intersection of Thompsons Road & Smiths Lane is almost complete. The construction of Smiths Lane road is progressing well with the asphalt to be poured over the next couple of months.